How much does 2000 sq ft of drywall cost in Joint Base Pearl Harbor Hickam, HI?

Hanging, taping and finishing drywall in Joint Base Pearl Harbor Hickam, HI
$6,438
2,000 ft² of board · typical range $4,292 – $10,060
Typical total$3.22 per ft² of board$6,438
Range you should see in bidsthree bids on the same scope normally land inside this$4,292 – $10,060
Labor portion65% of the job — this is the part that moves by city$4,185
Material portion35% — bought at national prices$2,253
Drywall and Ceiling Tile Installers pay near Joint Base Pearl Harbor Hickamabout $47/hr · Urban Honolulu, HI metro$97,000/yr
U.S. mean for the same tradeSOC 47-2081$63,600/yr
Versus the national pricetrade pay here runs +52.5% against the U.S. mean+$1,638

Notes

  • Where the number comes from. The national price for hanging, taping and finishing drywall is $2.40 per ft² of board — drywall installation pricing published for 2026, $1.60–$3.75 per ft² including materials. Labor is about 65% of that. Drywall and Ceiling Tile Installers near Joint Base Pearl Harbor Hickam, HI average $97,000 a year against a U.S. mean of $63,600 — a factor of 1.525 — so the labor half is scaled by that and the material half is not. Source: BLS OEWS May 2025 for the Urban Honolulu, HI metro area, SOC 47-2081.
  • Why the city matters, not just the state. Trade pay moves inside a state as much as it does between states. Crews do not commute across a state to bid a job, and materials ship at national prices either way — so a metro wage is the honest input here and a state average quietly rounds four different cities into one number.
  • What is in the price: board, screws, tape, three coats of compound to a level 4 finish, sanding, and labor.
  • What is not: primer and paint, texture, level 5 finish, and hauling the old board away. These are the lines that turn a $6,438 quote into a $8,048 invoice, so ask about each one before signing.
  • Use this as a bid check, not a quote. It prices an average job in average condition. Difficult access, the state of what is being replaced, the season, and a crew booked out three months all move the real number, and none of them are in a per-unit average.

hanging, taping and finishing drywall in Joint Base Pearl Harbor Hickam, HI

$6,438 is the typical number, and three bids on the same scope normally land between $4,292 and $10,060.

That is $1,638 more than the same job priced at the national average.

Why the city changes the number

About 65% of this job is labor — $4,185 of the $6,438 above. Labor is the only part that moves locally; a bundle of material costs what it costs wherever it is nailed down.

Drywall and Ceiling Tile Installers near Joint Base Pearl Harbor Hickam average $97,000 a year, against a U.S. mean of $63,600. That is a factor of 1.525, so the labor half is scaled by it and the material half is not.

Source: BLS OEWS May 2025 for the Urban Honolulu, HI metro area, SOC 47-2081.

What the quote should include

The lines that turn a quote into an invoice

Ask about each of them before you sign. On a job this size they are the difference between $6,438 and something a quarter higher.

Use it as a bid check, not a quote

This prices an average job in average condition. Access, the state of what is being replaced, the season, and a crew booked out three months all move the real number, and none of them are in a national average.

If a bid lands outside $4,292 – $10,060, that is not automatically wrong — but it is the question worth asking out loud.